Project Works Completed
▷ Hospitality
Project Name: Ramada Hotel Gulberg Lahore
Location: Gulberg, Lahore
Date: 2014 – 2018
Located in the heart of Gulberg, close to MM Alam road, Ramada Hotel Gulberg Lahore has 133 aesthetically furnished rooms along with high-end suites and apartments. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, with banquet halls designed to accommodate up to 1,500 guests.
Project Name: Grace Guest House
Location: F-6, Islamabad
Date: 2012 – 2014
Located in the heart of Islamabad, Grace Guest House has 16 aesthetically furnished rooms along with complete amenities. Grace Guest House offers a comfortable yet luxurious stay with immaculate interiors and refreshing exteriors.
Project Name: Ramada Resort Gilgit
Location: Gilgit, Baltistan
Date: 2021 – 2022
Located in the heart of Gilgit, close to Gilgit Road Sakwar, Mavi Hotel Gilgit has 68 aesthetically furnished rooms along with high-end event halls and conference rooms. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, and banquet halls designed to accommodate the guests.
Project Name: Bestwestern Premier Hunza
Location: Ganish, Hunza
Date: 2021 – 2023
Located in the heart of Ganish, Hunza, Mavi Hotel Hunza has 52 aesthetically furnished rooms along with high-end event halls and conference rooms. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, and banquet halls designed to accommodate the guests.
▷ Real Estate
Project Name: Royal Grace Villas
Location: Zone 4, Islamabad
Date: 2014 – 2018
Located in CDA zone 4 of Islamabad with a lush green environment that is surrounded by Margalla Hills. Royal Grace Villas is located close to many important areas of Islamabad like Chak Shahzad, Bani Gala and Park Road. It is 10 km from Islamabad Club, 13 km from Zero Point and 12 km from Faizabad.
Royal Grace Villas is offering 5, 8, 10 & 20 Marla, double story bungalows. Houses in Royal Grace Villas can be booked on cash payment and also on easy installments of 18 months.
Royal Grace Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Royal Grace Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Kar Saaz Villas
Location: Margalla Hills, Islamabad
Date: 2014 – 2018
Located in the heart of Margalla Hills in Islamabad, Kar Saaz Villas is a residential project in Islamabad. Kar Saaz Villas is offering 4 & 5 beds, double story bungalows. Houses in Kar Saaz Villas can be booked on cash payment and also on easy installments plans.
Kar Saaz Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Kar Saaz Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Grace Homes
Location: Margalla Hills, Islamabad
Date: 2021 – 2024
Grace Homes are located at the foothills of Margalla Hills and Shah Allah Ditta in Islamabad, an ongoing residential project in Islamabad. Houses in Grace Homes can be booked on cash payment.
Grace Homes is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Grace Homes is ideal for living and as a real estate investment in Islamabad.
Project Name: Royal Grace Villas
Location: Zone 4, Islamabad
Date: 2014 – 2018
Located in CDA zone 4 of Islamabad with a lush green environment that is surrounded by Margalla Hills. Royal Grace Villas is located close to many important areas of Islamabad like Chak Shahzad, Bani Gala and Park Road. It is 10 km from Islamabad Club, 13 km from Zero Point and 12 km from Faizabad.
Royal Grace Villas is offering 5, 8, 10 & 20 Marla, double story bungalows. Houses in Royal Grace Villas can be booked on cash payment and also on easy installments of 18 months.
Royal Grace Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Royal Grace Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Kar Saaz Villas
Location: Margalla Hills, Islamabad
Date: 2014 – 2018
Located in the heart of Margalla Hills in Islamabad, Kar Saaz Villas is a residential project in Islamabad. Kar Saaz Villas is offering 4 & 5 beds, double story bungalows. Houses in Kar Saaz Villas can be booked on cash payment and also on easy installments plans.
Kar Saaz Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Kar Saaz Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Grace Homes
Location: Margalla Hills, Islamabad
Date: 2021 – 2024
Grace Homes are located at the foothills of Margalla Hills and Shah Allah Ditta in Islamabad, an ongoing residential project in Islamabad. Houses in Grace Homes can be booked on cash payment.
Grace Homes is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Grace Homes is ideal for living and as a real estate investment in Islamabad.
▷ Power & Energy
Project Name: Gumat Nar HydroPower Project
Client: AJ & K, Private Power Cell, HEB, AJ & K
Location: Tehsil Sharda, District Neelum, AJ & K
Production Capacity: 49.5 MW
Date: 2017 – 2019
145 Km from Muzaffarabad City, in Tehsil Sharda, District Neelum, AJ & K, the site of the proposed Gumat Nar Hydropower project lies approximately 145 Km from Muzaffarabad in Tehsil Sharda of District Neelum. The stream – Surgon Nullah – a right bank tributary of Neelum River.
The site is accessible through Muzaffarabad-Athmuqam-Khel metal road up to Sharda. From Sharda a jeep able track of about 10 Kilometers leads to the proposed powerhouse site near the confluence of two major tributaries of Surgon Nullah, i.e. Gumat Nar and Nuri Nar.
▷ Infrastructure
Project Name: Construction of Circular Bypass Road Bannu
Date: 2019 – 2021
The Work consists of Subgrade Preparation in Earth Cut & Road Cut, Formation of Embankment from Roadway Excavation & Borrow Excavation, Roadway Excavation, Compaction of Natural Ground, Removal of Trees, Clearing & Grubbing, Asphaltic Base Course, Water Bound Macadam Base Course, Granular Sub Base Course using Pit Run Gravel, Double bituminous Surface Treatment, Asphaltic Wearing Course, Bituminous Tack Coat, Bituminous Prime Coat, Structural backfill using Common Material, Providing and Laying stone pitching / filling, Supply & fabricate M.S. reinforcement for cement concrete (Grade 60), RCC in roof slab, beam, column & other structural members, in situ or precast,
Plain Cement Concrete including placing, compacting, finishing & curing, Random rubble masonry, Steel Post of Metal Guard Rail, Road signs etc at Circular Bypass Road Bannu.
Project Name: Raising of Baran Dam Bannu
Date: 2018 – 2022
Baran Dam is a multipurpose project that aims at water storage, flood mitigation and power generation. The Project aims to regain / increase more than the original capacity of the existing dam upto 100,000 acre-ft with the raising the height of dam by 7m and diverting Tochi River flow through Tochi-Baran Feeder Canal which is designed for 1000 Cusecs.
Project Name: Flood Protection of Sialkot
Date: 2017 – 2019
The adaptation of this project will bring in substantial net benefit to Sialkot by reducing the flood damage. The project includes capacity enhancement, desilting and prism improvement works. Once completed, it will significantly improve the flood carrying capacity of the region.
Project Name: Construction of Protection Structure of Kabul River
Date: 2016 – 2022
The area selected for the proposed provision of flood protection arrangements was adversely affected during the flood of 2010. The intended flood protection work aims at the protection of village abadies & other infrastructure along the right bank of Kabul river where the flood water had infringed and inflicted historical calamity in Nowshera district. Upon the provision of flood management structures, it is anticipated that a feeling of security among the locals would be established which in turn would provide an incentive in levitating the agricultural income and thus instrumental in elevating the living standards of the local inhabitant.
On completion of the project the inhabitants of the area will feel a sense of security & the socio-economic condition of the locals would be improved.
Project Name: Construction of Manchura Dam in Mansehra District
Date: 2014 – 2018
The objective is to provide storage capacity of water, to assured irrigation supply of land and uplift the livelihood of inhabitant by providing employment and business opportunities
Project Name: Pehur High-Level Canal Extension
Location: Swabi District, KPK
Date: 1998-2011
Mardan is the largest town in the region with a population of about 1,000,000 persons and is located approximately 64 kilometers from Peshawar, which is the largest city and provincial headquarters of KPK.
Project details: Construction of new Irrigation System i.e. Earthworks, Canal Lining (PCC), Manufacturing/Laying of RCC Pipes (24” to 42” sizes), Fall, Aqueducts, Escape Channels, Bridges, Irrigation Pressure Control Valves, Road Crossing, Drain Crossing etc.
The main objective of this project is supply of irrigation water to the Project Area A new irrigation system will be constructed for enhancing agricultural production in the Project Area. The project also includes provision of drinking water supplies to seven villages in Swabi District.
Location: Kalabagh, District Mianwali
Contract Period: March 2013 – July 2018
Client: WAPDA
Nature of Works: Construction of O & M Staff Colony at Jinnah Hydro Power Project Site Near Jinnah Barrage, Kalabagh, District Mianwali.
Civil Works of Buildings, Plumbing Works, Internal Electrification Works, Internal Roads, Sewerage System, Septic Tanks, Soakage Pits, Water Supply System, Overhead Water tanks, Tube Wells, Street Lights etc.
Location: Regilalma, Peshawar
Contract Period: January 2011 – April 2017
Client: KPK WWB
Nature of Works: Construction of 1200 Family Flats at Regilalma, Peshawar (Phase-I).
Civil Works of 1200 Family Flats, Internal Plumbing Works, Internal Electrification Works, Internal Roads, External Electrification Works, Sewerage System, Septic Tanks, Soakage Pits, Water Supply System, Overhead Water tanks, Tube Wells, Street Lights etc.
Location: Hattar Road, Taxila
Contract Period: December 2009, Package (I & III) December 2013, Package (II & IV) April 2014
Client: WWF Islamabad
Nature of Works: Construction of Apartment Blocks Phase-I, Hattar Road, Taxila (Package-I to IV).
Civil Works of 504 Family Flats, Internal Plumbing Works, Internal Electrification Works, External Works (Storm Water Drains, Walkways & Footpaths, RCC Irrigation Channel).
Location: Hattar (Distt Haripur)
Contract Period: December 2006 – November 2012
Client: KPK WWB
Nature of Works: Construction of 600 Family Flats and Allied Infrastructure Works at Hattar (Distt Haripur) Package I & II.
Civil Works of 600 Family Flats, Internal Plumbing Works, Internal Electrification Works, External Works (Internal Roads, External Electrification Works, External Sewerage System, Septic Tanks, Soakage Pits, External Water Supply System, Overhead Water tanks, Tube Wells, Street Lights).
Location: Faisalabad
Contract Period: December 2004 – January 2008
Client: FIEDMC
Nature of Works: Value Addition City Faisalabad.
Development & Infrastructure Works, Roads, Water Supply, Sewerage System, O/H Tank, Drainage System, Boundary Wall, Gate, Street Lights & Foot Path etc. (Joint Venture of Khyber Grace-Ijaz & Co.)
Location: Sangjani, Islamabad
Contract Period: November 1997 – October 2006
Client: AWT
Nature of Works: Development Works AWT Housing Scheme Sangjani
Sector-III, Construction of Roads, Sewerage System, Water Supply System, Overhead Tanks, Treatment Plant & Culverts etc, Development of plots.
Location: Hattar (Distt. Haripur)
Contract Period: July 1997 – June 1999
Client: NWFP W.W.B
Nature of Works: Construction of 188 Family Quarters at Industrial Estate Hattar (Distt. Haripur) including internal water supply, electrification & sewerage system etc.
Location: Khyber Pakhtunkhwa
Contract Period: June 1995 – June 1998
Client: WAPDA
Nature of Works: Ghazi Barotha Hydropower Project Contract No. GBHP-WP-6 (Lot-6).
Construction of 76 Nos. Cat-IV, 38 Nos. Cat-V Houses including Internal Services & external roads, water supply sewerage system, External Electrification Works, street lighting, overhead tank with tube well & boundary wall.
Location: Kundian
Contract Period: January 1994 – April 1995
Client: WAPDA
Nature of Works: Construction 72 Nos. Category-IV Houses including internal services. Contract No. CHP-02 Chashma Hydropower Project Kundian.
Location: Chashma
Contract Period: April 1993 – November 1994
Client: P.A.E.C
Nature of Works: Construction 130 Houses for Chasnupp including internal services at Pak Atomic Energy Commission Kundian (Distt. Mianwali) including construction of a road costing Rs. 4 (M).
Location: Swabi, Khyber Pakhtunkhwa
Contract Period: January 1993 – December 1993
Client: WAPDA
Nature of Works: Construction 49 Nos. Cat-V Quarters at Right Bank Colony Tarbela including internal services.
Location: Charsadda, Khyber Pakhtunkhwa
Contract Period: November 1992 – September 1994
Client: NWFP W.W.B
Nature of Works: Construction of Labour Colony Charsadda including internal services & external roads, water supply, sewerage system, power supply, overhead tank & boundary wall etc
Location: Dallas Canal Division, Rahimyar Khan
Contract Period: Sep 2017 – April 2019
Client: Irrigation Punjab
Nature of Works: Strengthening, Raising and Providing Good Earth Cover Over Extension Minchen Flood Bund RD 380+000 To 501+000 And Restoration of Allied Structures
Location: Khaliqabad
Contract Period: April 2016 – July 2018
Client: WAPDA
Nature of Works: Rehabilitation Works of Mangla Reservoir Rim Along Mirpur-Kotli Road Near Khaliqabad Including Strengthening Works of Reservoir Rim Near Shanwari Restaurant – Contract Package No RSWMR-01
Location: Near Chilas at Harpan Das
Contract Period: June 2015 – Sep 2018
Client: WAPDA
Nature of Works: Diamer Basha Dam Project Contract CMV – II – 05 Construction of Diversion Works and Main Water Supply Line at Composite Model Village – II Near Chilas at Harpan Das
Location: Jampur
Contract Period: Mar 2015 – June 2017
Client: Irrigation Punjab
Nature of Works: Remodelling and Extension of Tayyab Drain at Jampur
Location: Peshawar
Contract Period: Nov 2014 – Sep 2017
Client: Irrigation Department KPK
Nature of Works: Package No. RWCS-5 Remodelling of Warsak Gravity Canal from RD 58+052 to RD 96+500 Earthwork, Concrete Lining and Structures at Peshawar
Location: Mangala, Kashmir
Contract Period: Nov 2012 – May 2013
Client: WAPDA
Nature of Works: Mangla Dam Raising Project – Contract No. MDR-39 – Replenishment Work of Existing Riprap from El. 1170 to El 1195 ft on upstream side of Main Dam & Intake Embankment
Location: Karachi
Contract Period: March 2012 – April 2013
Client: Irrigation & Power Department Sindh
Nature of Works: Raising & Strengthening of F.B Bund from RD-452 to 502 & providing stone pitching from RD-475 to 502 & Construction of Landhi (1 No) Package -14
Location: Sindh
Contract Period: July 2011 – Dec 2012
Client: WAPDA
Nature of Works: Rehabilitation/Strengthening of Embankment including Bed clearance of MNV Drain from RD-220 to 342 Contract No R-I (f/2)
Location: Miro Khan, Sindh
Contract Period: July 2011 – June 2012
Client: WAPDA
Nature of Works: Rehabilitation/Restoration of Damages Portion including Bed Clearance and Construction of Escape Structures of Hairdin Carrier Drain Extension from Chukhi to Miro khan Zero Point and 6 km North of Chukhi Contract No R-III(f/1)
Location: Miro Khan, Sindh
Contract Period: July 2011 – June 2012
Client: WAPDA
Nature of Works: Rehabilitation / Restoration of Damage Portions including Bed Clearance and Raising of Left Side Embankment from RD-58+000 to 161+000 of RBOD Extension from MKZP to Hairdin Pump Station Contract No R-III(f/2)
Location: Shahdādkot
Contract Period: July 2009 – Dec 2012
Client: WAPDA
Nature of Works: Construction/Remodelling of Shahdad Kot Main Drain from RD 0+000 to RD 58+000 Contract No. R-III(b/1)
Location: Usta Muhammad
Contract Period: Feb 2007 – Dec 2009
Client: WAPDA
Nature of Works: Construction of New Surface Drainage System for Usta Muhammad Drainage Unit-Usta Muhammad Main Drain Sub-Unit- Contract No R-III(d/2).
Location: Jacobabad/Larkhana District of Sindh
Contract Period: Feb 2006 – Dec 2010
Client: WAPDA
Nature of Works: Construction of RBOD Extension from Miro Khan Zero Point to Hairdin Pump Station Contract No R-III(b)
• Earthwork
• Compaction of embankment
• DR/VR Bridges
• MKZP Complex Structure
• Aqueducts Cum VR Bridges
• Outfall Structure
• Drainage Inlets / Drain Fall Structure
• Water Course Crossing
Location: Usta Muhammad
Contract Period: Feb 2006 – Dec 2010
Client: WAPDA
Nature of Works: Construction of New Surface Drainage System for Usta Muhammad Drainage Unit-Usta Muhammad Main Drain Sub-Unit- Contract No R-III(d/2).
Location: Sehwan
Contract Period: May 2005 – May 2007
Client: Irrigation Sindh
Nature of Works: Extension of RBOD from Sehwan to Sea Package No. DW/R-3-02 (RD 607 to 641).
• Earthwork
• Compaction of embankments
• Stone Pitching
Location: Miro Khan, Sindh
Contract Period: March 2005 – Aug. 2008
Client: WAPDA
Nature of Works: RBOD-III Project – Construction of Hairdin Carrier Drain Extension from Chukhi to MKZP & 6 Km North Chukhi Contract No. R-III(c)
Location: Southwest Nara Kanal, Sindh
Contract Period: March 2005 – Mar 2011
Client: WAPDA
Nature of Works: RBOD-I Project – Remodelling of Main Narra Valley Drain from RD 220 to 342 – Contract No. R-III (a/1)
Location: Miro Khan, Sindh
Contract Period: Feb. 2005 – Feb. 2007
Client: WAPDA
Nature of Works: Right Bank Outfall Drain RBOD-I Project Contract No. R-I(A) Construction of RBOD (MNVD) to Miro Khan Zero Point.
• Earthwork
• Compaction of embankment
• DR/VR Bridges
• Outfall Structure
• Cross Regulator
• Escape Structure
• Drainage Inlets (Box Type)
Location: Sehwan
Contract Period: April 2004 – Dec. 2006
Client: Irrigation Sindh
Nature of Works: Extension of RBOD from Sehwan to Sea Package No. DW/R3-07 (RD 754 to 805)
• Earthwork
• Compaction of embankments
Location: Attok, Punjab
Contract Period: Apr. 96 – Oct.98
Client: WAPDA
Nature of Works: Remodelling of Ballar Surface Drainage Lower Maqam, Lower Naranji Drains & Allied Structures Contract No. SWP/SD-02A, Swabi SCARP Project.
Earthwork
Structures:
D.R. Bridges
Piped Causeway
Gabion Drop Structure/Transition
Confluence Structures
Inlet Structure/Box Culverts
Location: Mardan District, Khyber Pakhtunkhwa
Contract Period: Oct. 95 – Dec. 98
Client: WAPDA
Nature of Works: Swabi SCARP Project – Remodelling of Surface Surkh Dehri, Sadiq Abad Landai Charnanka, Tributaries & Allied Structures Contract No. SWP/SD-04B:
Earthwork
Structures:
1) D.R. Bridge/V.R. Bridges
2) Confluence Structures
3) Gabion Drop Structures
4) Surface Drainage Inlets
5) Watercourse x-ing/Foot Bridge
Location: Dera Ismail Khan
Contract Period: Dec. 93 – July 94
Client: WAPDA
Nature of Works: Construction of Super Passage at RD 167+616 of CRBC Stage-I D.I. Khan.
Earthwork
RCC
Location: Dera Ismail Khan
Contract Period: Jan. 92 – Sep. 94
Client: WAPDA
Nature of Works: Construction of Flood Carrier Channel DN-1 to DN-4 & DN-5 CCAD Project Stage-II, D.I. Khan.
Earthwork
Location: Mardan
Contract Period: Oct. 89 – Dec. 92
Client: WAPDA
Nature of Works: Mardan SCARP Project Construction to Remodel Surface Drainage System & Allied Structures Contract No CW/SD/6 (Joint Venture with Mir Hassan Khan Sons being parent’s firm).
Earthwork
RCC/PCC
Stone Masonry
Project Name: Construction of Circular Bypass Road Bannu
Date: 2019 – 2021
The Work consists of Subgrade Preparation in Earth Cut & Road Cut, Formation of Embankment from Roadway Excavation & Borrow Excavation, Roadway Excavation, Compaction of Natural Ground, Removal of Trees, Clearing & Grubbing, Asphaltic Base Course, Water Bound Macadam Base Course, Granular Sub Base Course using Pit Run Gravel, Double bituminous Surface Treatment, Asphaltic Wearing Course, Bituminous Tack Coat, Bituminous Prime Coat, Structural backfill using Common Material, Providing and Laying stone pitching / filling, Supply & fabricate M.S. reinforcement for cement concrete (Grade 60), RCC in roof slab, beam, column & other structural members, in situ or precast,
Plain Cement Concrete including placing, compacting, finishing & curing, Random rubble masonry, Steel Post of Metal Guard Rail, Road signs etc at Circular Bypass Road Bannu.
Project Name: Raising of Baran Dam Bannu
Date: 2018 – 2022
Baran Dam is a multipurpose project that aims at water storage, flood mitigation and power generation. The Project aims to regain / increase more than the original capacity of the existing dam upto 100,000 acre-ft with the raising the height of dam by 7m and diverting Tochi River flow through Tochi-Baran Feeder Canal which is designed for 1000 Cusecs.
Project Name: Flood Protection of Sialkot
Date: 2017 – 2019
The adaptation of this project will bring in substantial net benefit to Sialkot by reducing the flood damage. The project includes capacity enhancement, desilting and prism improvement works. Once completed, it will significantly improve the flood carrying capacity of the region.
Project Name: Construction of Protection Structure of Kabul River
Date: 2016 – 2022
The area selected for the proposed provision of flood protection arrangements was adversely affected during the flood of 2010. The intended flood protection work aims at the protection of village abadies & other infrastructure along the right bank of Kabul river where the flood water had infringed and inflicted historical calamity in Nowshera district. Upon the provision of flood management structures, it is anticipated that a feeling of security among the locals would be established which in turn would provide an incentive in levitating the agricultural income and thus instrumental in elevating the living standards of the local inhabitant.
On completion of the project the inhabitants of the area will feel a sense of security & the socio-economic condition of the locals would be improved.
Project Name: Construction of Manchura Dam in Mansehra District
Date: 2014 – 2018
The objective is to provide storage capacity of water, to assured irrigation supply of land and uplift the livelihood of inhabitant by providing employment and business opportunities
Project Name: Pehur High-Level Canal Extension
Location: Swabi District, KPK
Date: 1998-2011
Mardan is the largest town in the region with a population of about 1,000,000 persons and is located approximately 64 kilometers from Peshawar, which is the largest city and provincial headquarters of KPK.
Project details: Construction of new Irrigation System i.e. Earthworks, Canal Lining (PCC), Manufacturing/Laying of RCC Pipes (24” to 42” sizes), Fall, Aqueducts, Escape Channels, Bridges, Irrigation Pressure Control Valves, Road Crossing, Drain Crossing etc.
The main objective of this project is supply of irrigation water to the Project Area A new irrigation system will be constructed for enhancing agricultural production in the Project Area. The project also includes provision of drinking water supplies to seven villages in Swabi District.
Location: Kalabagh, District Mianwali
Contract Period: March 2013 – July 2018
Client: WAPDA
Nature of Works: Construction of O & M Staff Colony at Jinnah Hydro Power Project Site Near Jinnah Barrage, Kalabagh, District Mianwali.
Civil Works of Buildings, Plumbing Works, Internal Electrification Works, Internal Roads, Sewerage System, Septic Tanks, Soakage Pits, Water Supply System, Overhead Water tanks, Tube Wells, Street Lights etc.
Location: Regilalma, Peshawar
Contract Period: January 2011 – April 2017
Client: KPK WWB
Nature of Works: Construction of 1200 Family Flats at Regilalma, Peshawar (Phase-I).
Civil Works of 1200 Family Flats, Internal Plumbing Works, Internal Electrification Works, Internal Roads, External Electrification Works, Sewerage System, Septic Tanks, Soakage Pits, Water Supply System, Overhead Water tanks, Tube Wells, Street Lights etc.
Location: Hattar Road, Taxila
Contract Period: December 2009, Package (I & III) December 2013, Package (II & IV) April 2014
Client: WWF Islamabad
Nature of Works: Construction of Apartment Blocks Phase-I, Hattar Road, Taxila (Package-I to IV).
Civil Works of 504 Family Flats, Internal Plumbing Works, Internal Electrification Works, External Works (Storm Water Drains, Walkways & Footpaths, RCC Irrigation Channel).
Location: Hattar (Distt Haripur)
Contract Period: December 2006 – November 2012
Client: KPK WWB
Nature of Works: Construction of 600 Family Flats and Allied Infrastructure Works at Hattar (Distt Haripur) Package I & II.
Civil Works of 600 Family Flats, Internal Plumbing Works, Internal Electrification Works, External Works (Internal Roads, External Electrification Works, External Sewerage System, Septic Tanks, Soakage Pits, External Water Supply System, Overhead Water tanks, Tube Wells, Street Lights).
Location: Faisalabad
Contract Period: December 2004 – January 2008
Client: FIEDMC
Nature of Works: Value Addition City Faisalabad.
Development & Infrastructure Works, Roads, Water Supply, Sewerage System, O/H Tank, Drainage System, Boundary Wall, Gate, Street Lights & Foot Path etc. (Joint Venture of Khyber Grace-Ijaz & Co.)
Location: Sangjani, Islamabad
Contract Period: November 1997 – October 2006
Client: AWT
Nature of Works: Development Works AWT Housing Scheme Sangjani
Sector-III, Construction of Roads, Sewerage System, Water Supply System, Overhead Tanks, Treatment Plant & Culverts etc, Development of plots.
Location: Hattar (Distt. Haripur)
Contract Period: July 1997 – June 1999
Client: NWFP W.W.B
Nature of Works: Construction of 188 Family Quarters at Industrial Estate Hattar (Distt. Haripur) including internal water supply, electrification & sewerage system etc.
Location: Khyber Pakhtunkhwa
Contract Period: June 1995 – June 1998
Client: WAPDA
Nature of Works: Ghazi Barotha Hydropower Project Contract No. GBHP-WP-6 (Lot-6).
Construction of 76 Nos. Cat-IV, 38 Nos. Cat-V Houses including Internal Services & external roads, water supply sewerage system, External Electrification Works, street lighting, overhead tank with tube well & boundary wall.
Location: Kundian
Contract Period: January 1994 – April 1995
Client: WAPDA
Nature of Works: Construction 72 Nos. Category-IV Houses including internal services. Contract No. CHP-02 Chashma Hydropower Project Kundian.
Location: Chashma
Contract Period: April 1993 – November 1994
Client: P.A.E.C
Nature of Works: Construction 130 Houses for Chasnupp including internal services at Pak Atomic Energy Commission Kundian (Distt. Mianwali) including construction of a road costing Rs. 4 (M).
Location: Swabi, Khyber Pakhtunkhwa
Contract Period: January 1993 – December 1993
Client: WAPDA
Nature of Works: Construction 49 Nos. Cat-V Quarters at Right Bank Colony Tarbela including internal services.
Location: Charsadda, Khyber Pakhtunkhwa
Contract Period: November 1992 – September 1994
Client: NWFP W.W.B
Nature of Works: Construction of Labour Colony Charsadda including internal services & external roads, water supply, sewerage system, power supply, overhead tank & boundary wall etc
Location: Dallas Canal Division, Rahimyar Khan
Contract Period: Sep 2017 – April 2019
Client: Irrigation Punjab
Nature of Works: Strengthening, Raising and Providing Good Earth Cover Over Extension Minchen Flood Bund RD 380+000 To 501+000 And Restoration of Allied Structures
Location: Khaliqabad
Contract Period: April 2016 – July 2018
Client: WAPDA
Nature of Works: Rehabilitation Works of Mangla Reservoir Rim Along Mirpur-Kotli Road Near Khaliqabadva Including Strengthening Works of Reservoir Rim Near Shanwari Restaurant – Contract Package No RSWMR-01
Location: Near Chilas at Harpan Das
Contract Period: June 2015 – Sep 2018
Client: WAPDA
Nature of Works: Diamer Basha Dam Project Contract CMV – II – 05 Construction of Diversion Works and Main Water Supply Line at Composite Model Village – II Near Chilas at Harpan Das
Location: Jampur
Contract Period: Mar 2015 – June 2017
Client: Irrigation Punjab
Nature of Works: Remodelling and Extension of Tayyab Drain at Jampur
Location: Peshawar
Contract Period: Nov 2014 – Sep 2017
Client: Irrigation Department KPK
Nature of Works: Package No. RWCS-5 Remodelling of Warsak Gravity Canal from RD 58+052 to RD 96+500 Earthwork, Concrete Lining and Structures at Peshawar
Location: Mangala, Kashmir
Contract Period: Nov 2012 – May 2013
Client: WAPDA
Nature of Works: Mangla Dam Raising Project – Contract No. MDR-39 – Replenishment Work of Existing Riprap from El. 1170 to El 1195 ft on upstream side of Main Dam & Intake Embankment
Location: Karachi
Contract Period: March 2012 – April 2013
Client: Irrigation & Power Department Sindh
Nature of Works: Raising & Strengthening of F.B Bund from RD-452 to 502 & providing stone pitching from RD-475 to 502 & Construction of Landhi (1 No) Package -14
Location: Sindh
Contract Period: July 2011 – Dec 2012
Client: WAPDA
Nature of Works: Rehabilitation/Strengthening of Embankment including Bed clearance of MNV Drain from RD-220 to 342 Contract No R-I (f/2)
Location: Miro Khan, Sindh
Contract Period: July 2011 – June 2012
Client: WAPDA
Nature of Works: Rehabilitation/Restoration of Damages Portion including Bed Clearance and Construction of Escape Structures of Hairdin Carrier Drain Extension from Chukhi to Miro khan Zero Point and 6 km North of Chukhi Contract No R-III(f/1)
Location: Miro Khan, Sindh
Contract Period: July 2011 – June 2012
Client: WAPDA
Nature of Works: Rehabilitation / Restoration of Damage Portions including Bed Clearance and Raising of Left Side Embankment from RD-58+000 to 161+000 of RBOD Extension from MKZP to Hairdin Pump Station Contract No R-III(f/2)
Location: Shahdādkot
Contract Period: July 2009 – Dec 2012
Client: WAPDA
Nature of Works: Construction/Remodelling of Shahdad Kot Main Drain from RD 0+000 to RD 58+000 Contract No. R-III(b/1)
Location: Usta Muhammad
Contract Period: Feb 2007 – Dec 2009
Client: WAPDA
Nature of Works: Construction of New Surface Drainage System for Usta Muhammad Drainage Unit-Usta Muhammad Main Drain Sub-Unit- Contract No R-III(d/2).
Location: Jacobabad/Larkhana District of Sindh
Contract Period: Feb 2006 – Dec 2010
Client: WAPDA
Nature of Works: Construction of RBOD Extension from Miro Khan Zero Point to Hairdin Pump Station Contract No R-III(b)
• Earthwork
• Compaction of embankment
• DR/VR Bridges
• MKZP Complex Structure
• Aqueducts Cum VR Bridges
• Outfall Structure
• Drainage Inlets / Drain Fall Structure
• Water Course Crossing
Location: Usta Muhammad
Contract Period: Feb 2006 – Dec 2010
Client: WAPDA
Nature of Works: Construction of New Surface Drainage System for Usta Muhammad Drainage Unit-Usta Muhammad Main Drain Sub-Unit- Contract No R-III(d/2).
Location: Sehwan
Contract Period: May 2005 – May 2007
Client: Irrigation Sindh
Nature of Works: Extension of RBOD from Sehwan to Sea Package No. DW/R-3-02 (RD 607 to 641).
• Earthwork
• Compaction of embankments
• Stone Pitching
Location: Miro Khan, Sindh
Contract Period: March 2005 – Aug. 2008
Client: WAPDA
Nature of Works: RBOD-III Project – Construction of Hairdin Carrier Drain Extension from Chukhi to MKZP & 6 Km North Chukhi Contract No. R-III(c)
Location: Southwest Nara Kanal, Sindh
Contract Period: March 2005 – Mar 2011
Client: WAPDA
Nature of Works: RBOD-I Project – Remodelling of Main Narra Valley Drain from RD 220 to 342 – Contract No. R-III (a/1)
Location: Miro Khan, Sindh
Contract Period: Feb. 2005 – Feb. 2007
Client: WAPDA
Nature of Works: Right Bank Outfall Drain RBOD-I Project Contract No. R-I(A) Construction of RBOD (MNVD) to Miro Khan Zero Point.
• Earthwork
• Compaction of embankment
• DR/VR Bridges
• Outfall Structure
• Cross Regulator
• Escape Structure
• Drainage Inlets (Box Type)
Location: Sehwan
Contract Period: April 2004 – Dec. 2006
Client: Irrigation Sindh
Nature of Works: Extension of RBOD from Sehwan to Sea Package No. DW/R3-07 (RD 754 to 805)
• Earthwork
• Compaction of embankments
Location: Attok, Punjab
Contract Period: Apr. 96 – Oct.98
Client: WAPDA
Nature of Works: Remodelling of Ballar Surface Drainage Lower Maqam, Lower Naranji Drains & Allied Structures Contract No. SWP/SD-02A, Swabi SCARP Project.
Earthwork
Structures:
D.R. Bridges
Piped Causeway
Gabion Drop Structure/Transition
Confluence Structures
Inlet Structure/Box Culverts
Location: Mardan District, Khyber Pakhtunkhwa
Contract Period: Oct. 95 – Dec. 98
Client: WAPDA
Nature of Works: Swabi SCARP Project – Remodelling of Surface Surkh Dehri, Sadiq Abad Landai Charnanka, Tributaries & Allied Structures Contract No. SWP/SD-04B:
Earthwork
Structures:
1) D.R. Bridge/V.R. Bridges
2) Confluence Structures
3) Gabion Drop Structures
4) Surface Drainage Inlets
5) Watercourse x-ing/Foot Bridge
Location: Dera Ismail Khan
Contract Period: Dec. 93 – July 94
Client: WAPDA
Nature of Works: Construction of Super Passage at RD 167+616 of CRBC Stage-I D.I. Khan.
Earthwork
RCC
Location: Dera Ismail Khan
Contract Period: Jan. 92 – Sep. 94
Client: WAPDA
Nature of Works: Construction of Flood Carrier Channel DN-1 to DN-4 & DN-5 CCAD Project Stage-II, D.I. Khan.
Earthwork
Location: Mardan
Contract Period: Oct. 89 – Dec. 92
Client: WAPDA
Nature of Works: Mardan SCARP Project Construction to Remodel Surface Drainage System & Allied Structures Contract No CW/SD/6 (Joint Venture with Mir Hassan Khan Sons being parent’s firm).
Earthwork
RCC/PCC
Stone Masonry
Project Name: Royal Grace Villas
Location: Zone 4, Islamabad
Date: 2014 – 2018
Located in CDA zone 4 of Islamabad with a lush green environment that is surrounded by Margalla Hills. Royal Grace Villas is located close to many important areas of Islamabad like Chak Shahzad, Bani Gala and Park Road. It is 10 km from Islamabad Club, 13 km from Zero Point and 12 km from Faizabad.
Royal Grace Villas is offering 5, 8, 10 & 20 Marla, double story bungalows. Houses in Royal Grace Villas can be booked on cash payment and also on easy installments of 18 months.
Royal Grace Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Royal Grace Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Kar Saaz Villas
Location: Margalla Hills, Islamabad
Date: 2014 – 2018
Located in the heart of Margalla Hills in Islamabad, Kar Saaz Villas is a residential project in Islamabad. Kar Saaz Villas is offering 4 & 5 beds, double story bungalows. Houses in Kar Saaz Villas can be booked on cash payment and also on easy installments plans.
Kar Saaz Villas is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Kar Saaz Villas is ideal for living and as a real estate investment in Islamabad.
Project Name: Grace Homes
Location: Margalla Hills, Islamabad
Date: 2021 – 2024
Grace Homes are located at the foothills of Margalla Hills and Shah Allah Ditta in Islamabad, an ongoing residential project in Islamabad. Houses in Grace Homes can be booked on cash payment.
Grace Homes is one of the top housing developments of Islamabad due to state of the art planning, prime location, and provision of all general amenities. Grace Homes is ideal for living and as a real estate investment in Islamabad.
Project Name: Ramada Hotel Gulberg Lahore
Location: Gulberg, Lahore
Date: 2014 – 2018
Located in the heart of Gulberg, close to MM Alam road, Ramada Hotel Gulberg Lahore has 133 aesthetically furnished rooms along with high-end suites and apartments. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, with banquet halls designed to accommodate up to 1,500 guests.
Project Name: Grace Guest House
Location: F-6, Islamabad
Date: 2012 – 2014
Located in the heart of Islamabad, Grace Guest House has 16 aesthetically furnished rooms along with complete amenities. Grace Guest House offers a comfortable yet luxurious stay with immaculate interiors and refreshing exteriors.
Project Name: Mavi Hotel Gilgit
Location: Gilgit, Baltistan
Date: 2021 – 2022
Located in the heart of Gilgit, close to Gilgit Road Sakwar, Mavi Hotel Gilgit has 68 aesthetically furnished rooms along with high-end event halls and conference rooms. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, and banquet halls designed to accommodate the guests.
Project Name: Mavi Hotel Hunza
Location: Ganish, Hunza
Date: 2021 – 2023
Located in the heart of Ganish, Hunza, Mavi Hotel Hunza has 52 aesthetically furnished rooms along with high-end event halls and conference rooms. The five-star hotel features spacious guestrooms, signature restaurants, fully equipped gymnasium, temperature-controlled swimming pool, recreational activities, an extensive range of meeting spaces, and banquet halls designed to accommodate the guests.
Project Name: Gumat Nar HydroPower Project
Client: AJ & K, Private Power Cell, HEB, AJ & K
Location: Tehsil Sharda, District Neelum, AJ & K
Production Capacity: 49.5 MW
Date: 2017 – 2019
145 Km from Muzaffarabad City, in Tehsil Sharda, District Neelum, AJ & K, the site of the proposed Gumat Nar Hydropower project lies approximately 145 Km from Muzaffarabad in Tehsil Sharda of District Neelum. The stream – Surgon Nullah – a right bank tributary of Neelum River.
The site is accessible through Muzaffarabad-Athmuqam-Khel metal road up to Sharda. From Sharda a jeep able track of about 10 Kilometers leads to the proposed powerhouse site near the confluence of two major tributaries of Surgon Nullah, i.e. Gumat Nar and Nuri Nar.